County Road Project Starts in Washington Twp. and the Chesters

Published on September 19, 2019

Road Work Ongoing in Chatham, Florham Park, Long Hill, Mt. Olive, and Roxbury

A series of county road paving and improvement projects are underway across Morris County, including work on a 2.1-mile segment of road that runs from East Mill Road/Route 513 in Washington Township to Route 206 in Chester.

Preliminary work also is ongoing on North Passaic Street in Chatham Borough and Florham Park, New Vernon Road in Long Hill, Drakesdale Road in Mount Olive, and Landing Road in Roxbury.Road work sign(JPG, 15KB)

Milling and paving work has been completed on Highview Avenue in Hanover, Mendham Road in Mendham Township, North Main Street and East-West Dewey Avenue in Wharton, and is nearing completion on Mount Olive/Flanders Road in Mount Olive and is virtually done on Dover-Rockaway Road in Rockaway Township.

The county also is moving toward construction soon on Canfield Avenue in Mine Hill, a small section of Littleton Road in Parsippany, and Mount Arlington Blvd. in Roxbury.

In addition, bids have been advertised for work on Quaker Church Road and Randolph Avenue in Randolph, the final two 2019 county paving projects, with work expected in late October.

This work is all part of the Board of Freeholders aggressive targeting of some 30 miles of county roads for upgrading this summer and fall. The county roadwork is in addition to local and state road projects.

See the complete list: /files/sharedassets/public/main-site/newsarchive-media/2019/2019-Road-Projects.pdf(PDF, 66KB)

On the bridge improvement front, work continues on the Crane Road bridge in Mountain Lakes. Bids have been received for the Mill Road Bridge replacement project in Morris Township and for the planned East Blackwell Street bridge project in Dover.

Freeholder Stephen H. Shaw(JPG, 117KB) Freeholder Stephen Shaw

The county also expects to move ahead with two more bridge projects this fall: Chestnut Terrace bridge in Rockaway Township and Waterloo Road bridge at the Netcong and Stanhope border.

We are working hard to keep our commitment to properly maintaining our road and bridge infrastructure in Morris County,'' said Morris County Freeholder Stephen Shaw. We intend to work through the paving season, before the weather turns colder, to complete our list for 2019.''

Current Projects:

  • Chatham Borough-Florham Park: North Passaic Street

Curb and Sidewalk Work Underway

1.1 miles from Main Street in Chatham to the county line in Florham Park

Contractor: American Asphalt & Milling Services

Bid Price: $1,013.982

  • Mount Olive: Mount Olive Rd/Flanders Rd

Work Nearly Complete

1.2 miles from Route 46 to Elias Drive

Contractor: Schifano Construction of Middlesex

Bid Price: $508,828

  • Washington Twp. and Chesters: East Mill Rd/Route 513:

Project Underway

2.1 miles, from E. Valley Brook Road to Route 206

Contractor: Top Line Construction of Somerville

Bid Price: $1.1 million

  • Mount Olive, Drakesdale Road:

Project Underway

0.7 miles, from Flanders-Netcong Road to Route 206

Contractor: Schifano Construction of Middlesex

Bid Price: $259,747

  • Roxbury, Landing Road:

Project Underway

1.2 miles, from Route 80 to Mt. Arlington Blvd

Contractor: Schifano Construction of Middlesex

Bid Price: $354,454

  • New Vernon Road, Long Hill:

Drainage Work Underway

1.4-miles, from Meyersville Road to the township border

Contractor: J.A. Alexander of Bloomfield

Bid Price: $550,298

  • Dover-Rockaway Road, Rockaway Twp.:

Paving Near Completion. Guiderail Work Next

0.4-miles, East Blackwell St. to Route 46

Contractor: J.A. Alexander of Bloomfield

Bid Price: $277,221

Mountain Lakes, Crane Road Bridge

The bridge spans a tributary of Troy Brook

Crane Road between Boulevard and Morris Avenue, near Cove Place

Contractor: Colonnelli Bros., Inc. of Hackensack

Bid Price: $268,290.

Upcoming Projects:

  • Littleton Road (County Route 630), Parsippany:

Anticipate Start 9/23

0.5-miles, Parsippany Blvd. to Smith Road

Contractor: AJM Contractors of Clifton

Bid Price: $323,746

  • Mine Hill, Canfield Avenue:

Anticipate Start 9/24

0.6 miles, W. Randolph Ave to Route 46

Contractor: J.A. Alexander of Bloomfield

Bid Price: $356,574

  • Arlington Blvd., Roxbury:

Anticipate Start 9/26

1.3 miles, Laurie Road to the township line

Contractor: J.A. Alexander of Bloomfield

Bid Price: $456,348

Completed Projects:

  • Boonton Twp., Powerville Road: 2-miles, Valley Rd. to Rockaway Valley Rd.
  • Chester Twp. and Randolph: North Road and Dover-Chester Road, 4.4 miles.
  • Dover, Randolph, V. Gardens, South Salem Street: 1.1 miles, E. Blackwell to Rte. 10.
  • Dover, South Morris Street: 0.9 miles from Route 46 to Millbrook Avenue.
  • Hanover Twp., Highview Avenue: 2-miles to East Hanover Avenue.
  • Harding-Morris Twp., James Street: 0.6-miles, Harter Rd. to Southgate Pkwy.
  • Lincoln Park, Boonton Turnpike: 2.1-miles, Main Street to the Wayne border
  • Lincoln Park-Pequannock, Comly Road/Ryerson Road: 7-miles from Main Street in Lincoln Park to the Boulevard in Pequannock.
  • Mendham Twp., Mendham Road: 0 mile from Ralston Hill Road to Bridge 629
  • Morris Township-Morristown: Madison Ave to Blackberry Lane, 1.2-miles.
  • Parsippany: Littleton Road, 1.7-miles from Route 10 to Crestview Drive.
  • Pequannock: Boulevard, 1.3 miles from Cooper Road to Route 23
  • Roxbury, Mt. Arlington Blvd.: Half-mile, Landing Rd. to Laurie Rd.
  • Wharton: North Main Street: 0.7 miles from Dewey Avenue to Route 15
  • Wharton, West and East Dewey Avenue: 0.9 miles W Central to Wharton Rail Trail

BRIDGES

  • Parsippany, Intervale Road over Troy Brook
  • Washington Township, Naughright Road over South Branch of the Raritan River
  • Washington Township, Black River Road Bridge, over tributary to the Black River
Tagged as: